<p>By Inegbenose Prevail</p>
<p><strong>The Transmission Company of Nigeria (TCN), Katsina Sub-Region, and Imcomtel Engineering Limited have inspected the Katsina 330/132/33kV Transmission Substation ahead of the next major installation phase of the project.</strong></p><p class="ari-link"><strong>Read also:</strong> <a href="https://sparknewsdaily.com.ng/tegbe-moves-to-tackle-power-infrastructure-vandalism-sets-up-security-committee/">Tegbe Moves to Tackle Power Infrastructure Vandalism, Sets Up Security Committee</a></p>
<p>The inspection, conducted on Thursday, September 24, 2026, was led by the Assistant General Manager (Transmission), Katsina Sub-Region, Engr. Usman Idris, who received the Imcomtel delegation headed by Engr. Emmanuel Okafor.</p>
<p>The team assessed various sections of the substation, including ongoing civil works, equipment locations and supporting infrastructure, to determine their readiness for the upcoming installation activities.</p><p class="ari-link"><strong>Read also:</strong> <a href="https://sparknewsdaily.com.ng/nigerias-marine-and-blue-economy-open-for-investment-oyetola-tells-danish-investors/">Nigeria’s Marine and Blue Economy Open for Investment, Oyetola Tells Danish Investors</a></p></p>
<p>A key focus of the inspection was the assessment of two 100MVA power transformers delivered to the project site on July 9, 2026, as well as their designated plinths.</p>
<p>The transformers are expected to significantly increase transmission capacity in Katsina State and strengthen electricity supply infrastructure across the North-West region.</p>
<p>The team also inspected four newly delivered control rooms to ascertain their readiness to accommodate critical protection, monitoring and control systems required for efficient operation of the substation.</p>
<p class="ari-link"><strong>Read also:</strong> <a href="https://sparknewsdaily.com.ng/tcn-restores-kainji-birnin-kebbi-330kv-line-after-tower-collapse/">TCN Restores Kainji–Birnin Kebbi 330kV Line After Tower Collapse</a></p><p>Following the inspection, TCN and Imcomtel agreed on the remaining technical requirements and site preparations needed to facilitate seamless coordination as the project progresses towards completion.</p>
<p>The inspection team also included the Principal Manager, Engr. Mustapha Idowu, and heads of technical departments.</p>