<p><strong>The Nigerian Electricity Regulatory Commission (NERC) says Nigeria’s grid-connected power plants utilised an average of 81 per cent of available generation capacity in September 2026.</strong></p>
<p>NERC disclosed this in its September 2026 Operational Performance Fact sheet posted on it&#8217;s X handle on Thursday, which showed that an average of 5,038 megawatts (MW) was available for dispatch during the month.</p><p class="ari-link"><strong>Read also:</strong> <a href="https://sparknewsdaily.com.ng/tinubu-celebrates-oyedepo-at-72-hails-his-impact-on-education-nation-building/">Tinubu Celebrates Oyedepo at 72, Hails His Impact on Education, Nation-Building</a></p>
<p>According to the Commission, average hourly generation stood at 4,089MW, representing an average load factor of 81 per cent of the available generation capacity.</p>
<p>The report also highlighted the performance of individual power plants, with Kainji_1 recording the highest load factor at 98 per cent.</p><p class="ari-link"><strong>Read also:</strong> <a href="https://sparknewsdaily.com.ng/fg-begins-construction-of-new-national-grid-control-centre-in-osogbo/">Nigeria Begins Construction of New National Grid Control Centre in Osogbo</a></p></p>
<p>Afam_2 and Egbin_1 followed closely, each recording a load factor of 94 per cent during the month.</p>
<p>&#8220;Average Available Capacity: An average of 5,038 MW was available for dispatch during the month.</p>
<p>&#8220;Average Load Factor: 81%, with average hourly generation reaching 4,089 MW, indicating that 81% of the available generation capacity was utilised on average.</p>
<p class="ari-link"><strong>Read also:</strong> <a href="https://sparknewsdaily.com.ng/xenophobic-attacks-national-assembly-suspends-visits-to-south-africa-boycotts-legislative-events/">Xenophobic Attacks: Nigeria&#8217;s Parliament Suspends Visits to South Africa, Boycotts Legislative Events</a></p><p>&#8220;Top Energy Producers: Kainji_1, Afam_2, and Egbin_1 recorded high utilisation levels, with load factors of 98%, 94%, and 94%, respectively&#8221;, NERC said.</p>
<p>NERC’s operational performance data provides an overview of the utilisation of Nigeria’s grid-connected generation fleet and the level of available capacity deployed for electricity generation during the period.</p>